Thursday, 21 January 2016

Pre Production - production Schedule


Date
Task
What we going to do?
Equipment
Cast and crew
04/01/16 - 05/02/16
Pre production
This will be the pre production part. I will finish the scripting and storyboarding. I will also do Recce’s, risk assessments and shooting schedules.
Macs
David Cuff
29/01/16 - 19/02/16
Filming days
I will be filming the band footage and the narrative in this time and I will require everyone for this so I can get the band footage done.
Nikon D3300
18-55mm Lens
70-300mm telephoto Lens
Rode Microphone
Rode DeadCat
Rode Boom pole
Camera Stabilizer
Tripod
Camera Dolly
Action camera
David Cuff, Callum Hope, Lochlan Hope, Emily Twist, Nathan Fisher ad Jack Bates 
07/03/16 - 18/03/16
Editing
This will be when I collect all of the footage together and start putting on a timeline and making the music video
Macs
David Cuff

No comments: